Cargill Deodorizer, Sidney, Ohio

Best estimates from others bidding on this rigging project for a Cargill plant was that installation of a new deodorizer would require 60 days downtime from start to finish.

UNITED Rigging Services promised a 30-day “goal” for installation, and actually completed the $1.2 million project in 19 days and accident-free!

Cargill was elated with the speedy turnaround, citing URS for its creativity, planning and “constructability,” which put the facility back on line more than twice as fast as other contractors had considered possible.

 

 

 

 

 

 

 

 

 

 

 